To ensure the installation quality of the Baowochi solenoid valve, it is recommended to follow the following standard operating procedures:
Preparation: Clean all connection surfaces to ensure there are no impurities or oil stains. Check if the seals are intact and installed correctly.
Tool selection: Use a calibrated torque wrench to ensure accurate measurement. Avoid using regular wrenches to tighten based on experience.
Tightening sequence: For multi bolt connections, use a diagonal cross sequence to tighten them in stages to ensure even force distribution.
Torque control: Apply torque in stages, first pre tighten to 50% of the specified value, and then gradually increase to the standard torque.
Final inspection: After tightening, confirm that the solenoid valve is in the correct position without any deviation or deformation.